Installation¶
On this page: the order in which to read and do the installation chapters, and the rules that apply on site.
Order of work¶
- Choose the board and build for this pool: Choose hardware and build.
- Unpack and check the box: What is in the box.
- Safety first: Electrical installation and safety. Decide which work needs a licensed electrician.
- Wire power, network, bus and inputs: Wiring the box.
- Own probes if the pool has none that can be read: Own probes and flow cell.
- Commission on site, step by step: Commissioning checklist.
Rules on site¶
- Lutra reads; the pool's own controllers keep control and keep their safety functions.
- Nothing on the DO terminals before Lutra firmware is on the board, and never a load directly.
- If the bus already has a master, Lutra only listens.
- The network and "changes from the cloud" are only set on site; take your time to finish the setup before the temporary network closes.